Phase 0 Infrastructure Dashboard
South-Central Somalia Region
Timeline: Month 3 of 36
Phase 0 Overview
Progress
16.5%
Budget Utilized
$12.4M
of $78.5M total
Companies Engaged
24
across 4 sectors
Communities Served
42
est. 185,000 people
Sector Progress
💧
Water Infrastructure
On Track
Completion
23%
Active Risks
2
▼
Latest Updates
Latest borehole repairs completed in Marka district.
⚡
Electricity Infrastructure
Delayed
Completion
18%
Active Risks
4
▼
Latest Updates
Generator delivery delayed by 2 weeks. Contingency plan activated.