Phase 0 Infrastructure Dashboard

South-Central Somalia Region

Timeline: Month 3 of 36

Phase 0 Overview

Progress

16.5%

Budget Utilized

$12.4M
of $78.5M total

Companies Engaged

24
across 4 sectors

Communities Served

42
est. 185,000 people

Sector Progress

💧

Water Infrastructure

On Track
Completion
23%
Active Risks
2
Latest Updates

Latest borehole repairs completed in Marka district.

Electricity Infrastructure

Delayed
Completion
18%
Active Risks
4
Latest Updates

Generator delivery delayed by 2 weeks. Contingency plan activated.